Hi, I want to create something like the below example, but Anaplan returns circular references. Could you please give me an idea? Example In the above example, I input below formulas Last month stock = PREVIOUS ( Stock ) Consumption = get from different module Planned Received Amount = OFFSET ( Recommended Order Quantity, - 1 , 0 ) Stock = Last month stock - Consumption + Planned Received Amount Lead time = get from different module Recommended Order Quantity = IF Stock > OFFSET ( Consumption, 1 , 0 ) THEN 0 ELSE OFFSET ( Consumption, 1 , 0 ) - Stock However, I want to change "Planned Received Amount" formula to OFFSET ( Recommended Order Quantity, - Lead time , 0 ) I can understand if lead time is less than 0 this would be a circular reference, but lead time is always over 0. Any ideas to resolve this? Ayumi