Dear Friends,

If I update time settings (Month & Year) in Dev and then using ALM sync with Test & Prod.

Will it get updated in Test & Prod?

2 ACCEPTED SOLUTIONS

Accepted Solutions
rob_marshall
Moderator

@Sravan_Kumar

Yes, if you updated the model calendar to the following year and you create a revision, when you sync to Prod, the new model calendar time will now be in the Prod model.

Rob

View solution in original post

rob_marshall
Moderator

@Sravan_Kumar

You got it...Happy Holidays!

View solution in original post

4 REPLIES4
rob_marshall
Moderator

@Sravan_Kumar

Yes, if you updated the model calendar to the following year and you create a revision, when you sync to Prod, the new model calendar time will now be in the Prod model.

Rob

Sravan_Kumar
Community Boss

Thank you Rob.

rob_marshall
Moderator

@Sravan_Kumar

You got it...Happy Holidays!

Sravan_Kumar
Community Boss

Yes Rob much help.